How long should a bathroom renovation take?

What is the process for a bathroom renovation and how long does it take?

First of all let’s consider the trades that go into a bathroom renovation.

Each renovation is performed by up to 12 trades and each one of those trades has to come back up to three times during the process.
[column width=”four” place=”first”]

  • Carpenter
  • Electrician
  • Plumber
  • Plasterer/Renderer

[/column][column width=”four”]

  • Waterproofer
  • Tiler
  • Cabinet Maker
  • Stone mason

[/column][column width=”four” place=”last”]

  • Glazier
  • Caulker
  • Painter
  • Cleaner

[/column]

Smarter Bathrooms Plumbing

Smarter Bathrooms Plumber

The plumber and the electrician are involved in the early stages of each bathroom renovation. At Smarter Bathrooms we get our electrician to come in on day on and disconnect all the live wiring to the bathroom and make it safe for the trades that are to follow. Its good practice to do this to not only protect our guys but also the people who are living in the home we are renovating.

The old bathroom fittings and the walls are removed by a carpenter and the plumber and sparkie do what we call a rough in. They disconnect all the old points, and run new pipes and wires to the new points. This usually takes a day per trade, but can be longer depending on the complexity of the job. The guys don’t really like working in the room together, so its best of one follows the other.

From there the carpenter takes over and builds the bath hob, the shower base, the floor if it needs to be altered and any new walls, doors or windows that need installing. He may also do work on the ceiling, getting it ready for the plasterer. This can be a day or more dependent on the amount of work being carried out. He will also straighten the walls making sure the room is true. This carries through to the tiler later on.

The plasterer follows next and seals up the room. He will either use gyprock, or sand and cement, depending on whether the structure is a stud and plaster or a solid brick home. This process involves multiple coats of plaster or render and drying times in between each. The plastering usually takes place over three days or so with sanding and recoating times to be taken account of.

Bathroom Renovation BuilderOnce he has finished, then the waterproofer comes through. He usually has to apply two coats and there is a 24 hour drying time in between these. This is obviously the most important step of the bathroom if we want it to last the distance. So many times we are replacing bathrooms where this is not done. You can’t tell by looking at the finished product if it was actually done as the waterproofing is applied behind the next layer. The tiles.

The tiler, one of the most important trades in the bathroom is next. We like to employ slow fastidious types who take their time and have a sense of pride in the finished product. Many a bathroom is ruined by a careless sloppy tiler. Keep in mind as well though that the tiler’s job is nearly impossible if the structure is not straight and square. Good foundations build towards a great finish. Each trade is important.

Next off we will install the cabinetry. Sometimes this is done prior to tiling. There are reasons why you might do one or the other. The stone mason is then called in to pick up the templates for the stone top and measure up. He comes back in one or two weeks to fit the stone.

While the stone is off being manufactured, the glass for the shower screen is measured and sent off to be made. The glazier comes back in two weeks and installs the made to measure shower screen.

The plumber and sparkie follow up next and “fit off” plumbing and electrical fittings. It’s really taking shape now, but still looking like a building site.

The carpenter does his fit off now, fitting doors, and accessories.

Next the caulker and the cleaner and painter follow on after this.

The painter can come at any stage near the end once it has been tiled. Once he has finished, there is nothing left to do, but a really good clean where all the excess grout is removed from the tiles and the new bathroom renovation is shined up and prepared for handover to the homeowner.

Usually the homeowner is pretty thrilled at this stage. Not only do they have a new bathroom to cut the ribbon on and take their first shower in, but also they say goodbye to the building team that have been sharing their every moment at home with for the last 4-5 weeks.

As I say, people are really pleased to see us when we arrive, but they are even more thrilled to see us go when the job is done, and we leave them with a sparkling new bathroom renovation!

Smarter Bathroom Renovation

A Smarter Bathroom Renovation

To chat with one of our designers, call 1300 662 838 or click here to book your in-home consultation

and one of our Award winning designers will come and discuss space, fixtures and finishes, designs, trends, budgets and more.

Book a Free Video or In-Home Consultation

I'm ready to renovate!

I would like a free video or in-home consultation and renovation budget.
  • This field is for validation purposes and should be left unchanged.

I'm looking for some advice!

Email me the renovation advice guide
  • This field is for validation purposes and should be left unchanged.